QUEST PARK DATA CAMPUS
Timeline & next steps

A consent-led path to operational halls by 2030.

Major permanent construction follows DCO approval; only low-regret enabling works proceed earlier under the existing consent.

2026
01

Strategy & surveys

DCO strategy, scoping and site surveys begin. Section 35 direction request submitted April 2026.
2026–27
02

Consultation & application

Stakeholder consultation and preparation of the Development Consent Order application.
2027–28
03

Examination & decision

Examination by the Planning Inspectorate. DCO decision around mid-2028.
From consent
04

Enabling works & procurement

Site enabling works, energy design and procurement, lead-item ordering.
~2030
05

First operational halls

First data halls energised and brought into operation, with phased expansion to follow.
Why a single DCO

One application. Campus and energy centre.

Since 8 January 2026, data centres can be directed into the Nationally Significant Infrastructure Project regime. Quest Pit submitted a Section 35 direction request in April 2026, seeking to bring both the data centre campus and its on-site gas generating station into a single Development Consent Order - supported by the Government's designation of data centres as Critical National Infrastructure.